Wastewater Treatment System Grants and Design

A 39 year-old wastewater treatment lagoon was suspected of leaking. The state regulatory agency requested that expensive studies be completed to identify the problem; however, because of the lagoons age and likelihood of leaking, Jesik Consulting recommended that the studies be skipped in place of upgrading the facility.

An alternative analysis was completed for a mechanical treatment system, an evaporation pond and a construction of a pipeline to an existing facility. The pipeline alternative was selected by the board and Jesik Consulting prepared a Small Community Grant to pay for a new pipeline and lift station. Construction is scheduled to be completed in the fall of 2017. Stay tuned for photos of our progress on this project.